In the News: Penn State University’s Beaver Stadium Tops Out

With 750,000 work hours, 6,200 tons of steel, and nearly 12,000 cubic yards of concrete now in place, the Barton Malow-AECOM Hunt-Alexander tri-venture team has topped out Beaver Stadium’s 195-foot West Shore Home Field structure.

The Barton Malow-AECOM Hunt-Alexander tri-venture team has reached a major milestone on Penn State University’s Beaver Stadium revitalization project: the placement of the final beam atop the 195-foot structure, marking its maximum height and signaling the transition from one of the project’s most complex phases of construction.

To date, the team has logged more than 750,000 work hours, erected 6,200 tons of steel, and poured nearly 12,000 cubic yards of concrete. Penn State Athletics and Vice President for Intercollegiate Athletics Dr. Patrick Kraft joined the team on site to celebrate the topping out of the West Shore Home Field at Beaver Stadium Revitalization.

Trades team members signing the beam
Trades team members signing the beam
Barton Malow Senior Project Manager Mike Abbondante giving remarks at the topping out
Barton Malow Senior Project Manager Mike Abbondante giving remarks at the topping out
Workers lift the beam into its final place
Workers lift the beam into its final place
Penn State Athletics and Vice President for Intercollegiate Athletics Dr. Patrick Kraft signing the beam
Penn State Athletics and Vice President for Intercollegiate Athletics Dr. Patrick Kraft signing the beam

Photos by Mark Selders courtesy of Penn State Athletics

Demolition began following the 2024 season, with the removal of the press box, upper deck, and several ground-level structures. Work will continue through the 2026 football season, and Nittany Lions fans will see significant changes when they arrive in the fall, including expanded concourses, upgraded technology, new sports lighting, and more. The project is scheduled for full completion before the 2027 season.

The project is also making a meaningful economic impact in the region. Between 800 and 1,000 unique tradespeople will work the project each summer, with up to 400 on site daily at peak — generating an estimated $15 million in regional economic impact. In the first phase, 75% of materials and labor were sourced from Pennsylvania.

Penn State head football coach Matt Campbell recently visited the site to see the progress firsthand — a testament to the excitement building around what Beaver Stadium will become.

Media Coverage

Sports Illustrated: Penn State’s Beaver Stadium Renovation Reaches Lofty Milestone

Centre Daily Times: What to know about Phase II of Penn State’s Beaver Stadium renovation project

Sports Business Journal: Beaver Stadium renovation reaches phase two milestone, west side expansion

Allied News: Penn State ‘tops off’ Beaver Stadium project

Penn State University’s Beaver Stadium is undergoing a major revitalization led by a tri-venture team of Barton Malow, AECOM Hunt, and Alexander. The project will deliver expanded concourses, upgraded technology, new sports lighting, and other fan experience improvements, with full completion targeted before the 2027 football season.

Topping out marks the placement of the final structural beam at a building’s maximum height — in this case, 195 feet. For the Beaver Stadium revitalization, it signals the successful completion of one of the project’s most complex construction phases and the transition to the next stage of work.

The project team has logged more than 750,000 work hours, erected 6,200 tons of steel, and poured nearly 12,000 cubic yards of concrete. Demolition of the press box, upper deck, and several ground-level structures began after the 2024 football season.

Nittany Lions fans arriving for the 2026 football season will already see significant changes, including expanded concourses, upgraded technology, and new sports lighting. The full revitalization is scheduled for completion before the 2027 season.

The project is generating an estimated $15 million in regional economic impact. Between 800 and 1,000 unique tradespeople will work the project each summer, with up to 400 on site daily at peak. In the first phase, 75% of materials and labor were sourced from within Pennsylvania.